Boynton Main Entrance, Auditorium, and Kitchen/Café

Project Overview

As part of Phase 2 of the capital project, Boynton’s main entrance is being upgraded to improve security and create a new welcome area. The kitchen/cafeteria and the auditorium are also being renovated, and the new auditorium area will be "zoned" for after-hours security. Some of the school's bathrooms are being upgraded, and a new exterior electronic sign is being installed.

December 2024 Update from Campus Construction

  • Auditorium lighting training was conducted on 12/5/2024.

  • Tt performed substantial completion inspection of all electrical work in the auditorium, and Campus issued report to the Electrical Contractor.

  • Theatrical rigging. Training was completed on 12/10/2024.

  • Change Order work pending by GC to relocate the cyclorama to allow the image projected on the stage to be clear and fill the screen.

Construction Schedule

June 2023 - Winter 2024