Future Construction

Phase 3a.1

Key Scope Items

  • Enfield roof replacement

Status (as of 6/13/24)

  • Contractor has been working on remaining submittals.

  • Work is scheduled for Summer 2024.

  • Materials expected to start arriving to site June 27/28.

Phase 3b.1

Key Scope Items

  • STEM renovation/addition at Ithaca High School

  • HVAC upgrades (adding air conditioning) and new temperature controls at Ithaca High School

  • Addition of a canopy and additional seating at the visitor entrance/student drop-off area, façade upgrades on cafeteria walls, installation of motorized shades for the cafetorium, and toilet room upgrades at Enfield Elementary

  • Precast stonework at Beverly J. Martin Elementary

  • Boynton kitchen additions (power, hood, floor drains)

Status (as of 6/13/24)

  • High School: Work has begun.

  • Enfield: Construction scheduled for summer 2025.

  • Boynton: Upon the district attempting to program the chargers, it was found that there was an electrical issue with the existing panel/feeds. Tetra Tech has issued a solution and we are awaiting information from the Electrical Contractor on delivery timeframe of the required part.

Fall Creek Emergency Repairs

Key Scope Items

  • Emergency repairs to portion of building involved in an accident

Status (as of 6/13/24)

  • Contract for General Contractor awarded to Massa, and State Contract for a small amount of building controls to Day.

  • Work is scheduled to begin summer 2024

Phase 3b.2

Key Scope Items

  • Remaining HVAC work and paving improvements at Ithaca High School

  • Site improvements on Lake Street at the district office and Area K parking lot and Area K entrance improvements

  • Cafeteria lighting improvements at Beverly J. Martin Elementary

  • Cafeteria lighting improvements, new playground, and floor abatement/replacement at Fall Creek Elementary

Status

  • Tetra Tech anticipates submitting this phase to the SED in the fall of 2024 with an anticipated approval date of May/June 2024

  • Work is tentatively scheduled to begin in the fall/winter of 2025, depending on material availability

  • In partnership with Dr. Janet Loebach of Cornell Human Ecology's Department of Human Centered Design, students at Fall Creek Elementary are co-designing their school's new playground.

    • In November 2023, students in Mr. Bell’s fifth grade class presented their ideas for the playground to researchers, ICSD administrators, and Tetra Tech architects. Check out photos here!

    • In April 2024, Professor Loebach presented to the Board Facilities Committee on the co-design process with the Fall Creek students and their recommendations/design exemplars. View the presentation on YouTube (click here for the slideshow)